The Borough Yard project will transform former industrial land into a new neighbourhood of up to 1,600 homes, with enabling works set to unlock the first phase of development.
John Sisk has secured a £37m contract to prepare a major brownfield site in Birkenhead for a new residential neighbourhood, marking an important step forward for one of the town’s largest regeneration projects.
Wirral Council has approved the fixed-price contract for enabling works at Borough Yard, formerly known as Hind Street Urban Village. The development will transform former gasworks and railway land between Birkenhead Central and Green Lane railway stations, creating the foundations for a long-term programme of residential, commercial and public space development.
Major engineering and remediation works
Sisk’s contract covers extensive ground remediation and engineering works required to prepare the site for construction. The programme also includes a new active travel corridor and the first section of the planned Dock Branch South linear park.
The work is an essential part of making the former industrial land suitable for redevelopment, addressing the infrastructure and ground conditions that need to be resolved before the wider masterplan can progress.
The initial enabling programme is intended to unlock at least 633 homes, forming the first stage of a much larger neighbourhood planned for the site.
Rising costs prompt additional regional funding
The wider enabling works programme has seen its estimated cost increase from £57m to £66m, reflecting inflation, delays and rising drainage infrastructure costs.
Liverpool City Region Combined Authority has agreed to provide an additional £8.9m to address the funding shortfall, allowing the project to move forward.
Separate utility infrastructure works will also be required. A further £13.7m has been earmarked for United Utilities to carry out major sewer diversions and install an underground stormwater storage tank. Cadent gas infrastructure will also need to be relocated as part of the wider preparations.
These works demonstrate the scale of the infrastructure investment required to bring a substantial former industrial site back into productive use.
Further development works planned for 2027
Wirral councillors have also approved a £2.9m development management agreement with Ion Property Developments, which is overseeing the regeneration scheme.
Some elements of the planned infrastructure have been deferred to help manage costs. Highway realignment works at Kings Square and part of the Dock Branch South linear park have been pushed back to 2027.
The deferred works are estimated to cost a further £12m and could eventually be incorporated into Sisk’s contract, depending on how the project progresses.
Borough Yard masterplan to deliver up to 1,600 homes
The wider Borough Yard masterplan has hybrid planning consent for up to 1,600 homes, alongside commercial space, community facilities and new public areas. The development is expected to take between 10 and 15 years, reflecting the scale and complexity of transforming the site.
The regeneration is expected to bring new housing and amenities to a strategically located part of Birkenhead, while reconnecting previously underused land with the surrounding town centre and transport network.
For Sisk, the £37m appointment represents a significant role in the early delivery of the scheme. For Wirral, the enabling works mark a key milestone in turning a long-term regeneration ambition into a deliverable development programme.
With remediation, engineering and infrastructure works now moving forward, Borough Yard is taking an important step towards becoming a new residential and commercial neighbourhood for Birkenhead.
Source: Construction Enquirer.